Phase 4: Plan

Status: approved and under way; re-planned after M3 on 2026-11-12 (section 1) · Inputs: 01-requirements.md, 02-architecture.md, 03-api/

1. Shape of the plan

  • Budget: 10 hours a week, starting 2026-11-16. Superseded for scheduling by the re-plan after M3 below: the hours stay as a measure of each task's size, the dates are gone.
  • Estimates are your hours, with Claude Code writing most of the code and you reviewing, testing and deciding.
  • Every estimate includes tests and docs.
  • A 25% buffer is added to each milestone. Two weeks off at the year end.
  • Two releases instead of one:
  • v0.1.0-alpha, the closed loop: capture → outcomes → calibrate → compile with a guarantee → gate in the app. Ships after M3, when its gates are met (the re-plan below; this plan first said 2027-07-05). Getting the core in front of users early is the main answer to the competition risk (R1).
  • v0.1.0 adds drift, alerts, shadow models and the review queue. Ships after M7; the date is set after the alpha (this plan first said 2027-10-18).
  • Re-plan after every milestone. Actual hours against estimates set the next milestone's dates. M1 is the first real measure of speed, so treat the dates after it as provisional.
  • Phases 6 to 8 of the brief move into the milestones:
  • The testing strategy (docs/05-testing.md) is written first, in M1, so CI and the coverage gate exist from the first commit.
  • Release work splits between the alpha and M7.
  • The operations doc is written in M7.
  • M6 (dashboard) is v2, as decided in Phase 0. A rough size for v0.2 (dashboard plus TypeScript SDK) is 110–140 hours, re-estimated after launch. The agent gate and the assistant (ADR 0014) add about 35 more; see "After v0.1.0" below.
Milestone Planned hours With buffer Status
M1 Capture 107 134 Done 2026-11-11. Open: T1.14 (real calls) and NFR-02 on a rented VM
M2 Calibrate and compile 69 86 Done 2026-11-11
M3 Gate 49 61 Done 2026-11-12
Alpha release 16 20 Next. Ships when its gates are met (below)
M4 Watch 38 48 Not started
M5 Compare and review 34 43 Not started
M7 Launch 38 48 Not started
Total 351 440 v0.1.0 follows M7. No date until the alpha's real pace is known

Re-plan after M3 (2026-11-12)

What happened. M1 to M3 (225 planned hours, 29 weeks of the original calendar) were built between 2026-11-10 and 2026-11-12, with Claude Code writing the code and CI testing every change. The plan counted the maintainer's hours at 10 a week; that was not the limit, so dates computed from it were the wrong tool. Nothing was cut: all three demos run in CI, and the nightly coverage experiment (NFR-09) passes.

Still open from M1 to M3, and only the maintainer can close it:

  • T1.14: real calls to TypeSafe and OpenAI, which need their keys (a few cents).
  • NFR-02: ingest at 500 records a second on a rented 2 vCPU VM. On GitHub runners it sat at the edge, proxy or not (ADR 0015).
  • R6: someone who knows hypothesis testing reads ADR 0006 and the compiler before the alpha.

What changes:

  1. Gates replace dates. The alpha ships when TA.1 to TA.3 are done and the three items above are closed and the maintainer has done the one-time setup in releasing.md (a PyPI pending publisher, the pypi environment, GHCR visibility) and has decided how it is announced. Dates for M4, M5 and M7 are set after the alpha, from how long it really took.
  2. TV.1 (the agent gate and Claude Code hook) moves to right after the alpha, before M4. It is 12 planned hours, and this plan said it would move if the re-plan found room. The dashboard's drift and alert screens wait one task longer for their endpoints.
  3. The dashboard (M6) was started early, in a parallel session, on the public API: a preview runs at demo.trimset.dev on recorded data. The "served by your install" part stays in v0.2. Its remaining screens take endpoints in the order they land: drift reports, alerts and rules, review items, the shadow report.
  4. T7.1 is split by what is stable. The API reference (rendered from openapi.yaml) and the docs-site skeleton with the pages that exist are done before the alpha (ADR 0016); concept pages and integration guides wait until M4 and M5 have settled what there is to explain.

2. Tasks

M1 Capture: ingest, proxy, outcomes, storage

ID Task Covers Hours
T1.1 Monorepo scaffold: uv workspace, the three packages, ruff, mypy, pytest, pre-commit, LICENSE ADR 0002, 0013 6
T1.2 CI on GitHub Actions (lint, types, unit, integration with a Postgres service, image build); write docs/05-testing.md first NFR-08 6
T1.3 Docker image; compose (postgres, migrate, server, worker); /health, /ready; JSON logs; OpenTelemetry NFR-01, NFR-13, NFR-17 6
T1.4 Migration runner and first schema; monthly partitions ADR 0003 8
T1.5 Projects; keys (four scopes, hashed, cached, revocation); trimset-server bootstrap commands FR-51–53 6
T1.6 Wire module in trimset: canonical JSON, question/1, question_id, state hash, responses into records; vector tests FR-03, FR-09 8
T1.7 POST /v1/decisions:log: validation, question registration, batched inserts FR-01, FR-02 8
T1.8 Proxy (detail below the table) FR-04–08, NFR-03, NFR-06 14
T1.9 Outcomes: join, held outcomes, corrections, default-by-rule job; POST /v1/decisions:actions FR-10–13, FR-33 12
T1.10 Mock upstream: both formats, seeded, latency and error injection, version switch FR-59 6
T1.11 Data generator: all six scenario shapes, three in full (UC-1, UC-2, UC-3); planted miscalibration, delays, model swap FR-60 10
T1.12 Contract tests against openapi.yaml; integration tests — 6
T1.13 Load test on a 2 vCPU VM; keep Python or take the Rust escape hatch NFR-02, NFR-03 6
T1.14 Real calls: Jev, Ollaya, and OpenAI's error format (the Phase 3 assumption) — 2
T1.15 Demo examples/m1-capture — 3

T1.8 covers: - both key modes, forwarding and the header rules; - decision ids; - the buffer and its writer; - errors in the upstream's format; - multipart requests; - model versions; - operator-defined upstreams, with each key bound to its URL and no redirects followed (ADR 0011).

M2 Calibrate and compile

ID Task Covers Hours
T2.1 Metrics and reliability bins; golden tests against scikit-learn FR-17 8
T2.2 Calibrators (temperature, Platt, isotonic) and method selection by cross-validation; golden tests FR-16 10
T2.3 Dataset builder: matured labels, window, de-duplication, splits, coverage FR-14, FR-18, FR-19 8
T2.4 Compiler (detail below the table) FR-20–25 16
T2.5 Coverage experiment, 200 seeds, run nightly in CI NFR-09, SM-2 6
T2.6 Fit and compile jobs; storing fits and policies; simulator endpoint FR-26 8
T2.7 CLI: config, calibrate, simulate, compile, policy show and diff, decisions tail, coverage, export, --json FR-55, FR-58 10
T2.8 Demo examples/m2-refund-fraud UC-1 3

T2.4 covers: - the rule forms; - Learn-then-Test; - the Bonferroni split; - feasibility; - the labels-needed count; - cost targets; - guarantee statements.

M3 Gate: SDK and policy lifecycle

ID Task Covers Hours
T3.1 Policy lifecycle: transitions, events, audit log, rollback FR-27–29, FR-54 8
T3.2 Policy bundle with ETag; guarantee status FR-32, ADR 0008 4
T3.3 Scheduled refits that create proposals, with a diff and the label-source mix FR-30 6
T3.4 SDK: client, policy cache, the gate algorithm, audit sampling, defaults and reasons FR-31–35, FR-37 12
T3.5 SDK transport: log, log_exchange, outcome, action reports, buffers, backoff; instrument() for in-process models such as Hugging Face pipelines FR-36 10
T3.6 SDK tests: vectors, gate examples, chaos, gate benchmark, propagation time NFR-04, NFR-05, NFR-07 6
T3.7 Demo examples/m3-ticket-triage UC-2 3

Alpha release

ID Task Covers Hours
TA.1 Release pipeline: multi-arch image on GHCR, PyPI trusted publishing, changelog, semver tags NFR-16 6
TA.2 Quickstart and self-hosting pages; README NFR-20 6
TA.3 Homepage: claims match the alpha, [X]% from demo data (the proxy-key snippet and the trimset.dev deploy, on Cloudflare, were done early on 2026-11-11) — 4

M4 Watch: drift and alerts

ID Task Covers Hours
T4.1 Alerts: rules, signed webhooks, Slack, email, cool-down, resolve notices FR-42–44 10
T4.2 Drift job: windows, PSI, JS divergence, permutation tests, reports FR-38, FR-41 8
T4.3 Health checks FR-40 6
T4.4 Live policy check (confidence sequences); suspending guarantees FR-40, ADR 0007 6
T4.5 Silent-upgrade alerts FR-39 2
T4.6 Experiments for SM-3 (false alarms) and SM-4 (time to detect a swap) SM-3, SM-4 4
T4.7 Demo examples/m4-silent-upgrade UC-2 2

M5 Compare and review

ID Task Covers Hours
T5.1 Shadow traffic in the proxy; copying labels to shadows FR-45 6
T5.2 Shadow report (McNemar, flip rate, deltas) FR-46 5
T5.3 Review queue: filling rules, claims and leases, label, skip, http(s)-only links, raw-state gate FR-47–50 8
T5.4 Keyboard review session in the CLI FR-48 5
T5.5 Retention, partition drops, deletions FR-56, FR-57, NFR-14 7
T5.6 Demo examples/m5-model-routing UC-3 3

M7 Launch

ID Task Covers Hours
T7.1 Docs site: concepts, an API reference built from openapi.yaml, integration guides (Jev, Ollaya, Ollama, OpenAI, Hugging Face transformers, LangGraph, decision-circuits) NFR-20 14
T7.2 Security: dependency audit, secret scan, license check in CI; threat-model review NFR-11, NFR-18 4
T7.3 docs/06-operations.md: runbooks, SLOs Brief, Phase 8 5
T7.4 Community files, issue labels, ROADMAP.md — 5
T7.5 Homepage: final numbers (the site v2 pages, use cases included, were built early on 2026-11-11) — 6
T7.6 Fresh-machine quickstart check; upgrade test from the alpha; launch NFR-15, NFR-20 4

After v0.1.0: agents and the assistant

Not in v0.1's hours or dates (ADR 0014). TV.1 can start once M3 ships; if the re-plan after M3 finds room, it moves before the launch.

ID Task Covers Hours
TV.1 MCP server (gate, outcome and explain tools) and a Claude Code PreToolUse hook demo: a decision model and an approved policy decide whether an agent's tool call runs, asks a human, or is blocked UC-5, FR-31–35 12
TV.2 Assistant in the v2 dashboard: a text model with read-only tools over fits, simulations, drift reports and policy diffs, explaining trade-offs in plain words; it may draft a proposal, never approve one. Off by default; the operator picks the model FR-61, FR-27–29, FR-54 24

3. Dependencies

graph LR
  T1_1[T1.1 scaffold] --> T1_2[T1.2 CI + testing doc]
  T1_1 --> T1_3[T1.3 image + compose]
  T1_1 --> T1_4[T1.4 schema]
  T1_1 --> T1_6[T1.6 wire module]
  T1_4 --> T1_5[T1.5 keys]
  T1_5 & T1_6 --> T1_7[T1.7 log API]
  T1_5 & T1_6 --> T1_8[T1.8 proxy]
  T1_10[T1.10 mock upstream] --> T1_8
  T1_4 & T1_5 --> T1_9[T1.9 outcomes + actions]
  T1_6 --> T1_11[T1.11 data generator]
  T1_7 & T1_8 & T1_9 --> T1_12[T1.12 contract + integration tests]
  T1_12 --> T1_13[T1.13 load test]
  T1_8 --> T1_14[T1.14 real calls]
  T1_12 & T1_11 --> T1_15[T1.15 demo M1]
  T2_1[T2.1 metrics] --> T2_2[T2.2 calibrators]
  T1_9 --> T2_3[T2.3 dataset]
  T2_2 & T2_3 --> T2_4[T2.4 compiler]
  T2_4 & T1_11 --> T2_5[T2.5 coverage experiment]
  T2_4 --> T2_6[T2.6 jobs + simulator]
  T2_6 --> T2_7[T2.7 CLI]
  T2_7 & T2_5 --> T2_8[T2.8 demo M2]
  T2_6 --> T3_1[T3.1 lifecycle]
  T3_1 --> T3_2[T3.2 bundle]
  T3_1 --> T3_3[T3.3 scheduled refits]
  T3_2 & T1_6 --> T3_4[T3.4 SDK gate]
  T1_7 & T1_9 --> T3_5[T3.5 SDK transport]
  T3_4 & T3_5 --> T3_6[T3.6 SDK tests]
  T3_6 --> T3_7[T3.7 demo M3]
  T3_7 & T2_8 & T1_13 --> TA[Alpha release]
  T1_4 --> T4_1[T4.1 alerts]
  T2_3 & T4_1 --> T4_2[T4.2 drift]
  T4_1 --> T4_3[T4.3 health]
  T3_1 & T4_1 --> T4_4[T4.4 live check]
  T1_8 & T4_1 --> T4_5[T4.5 silent-upgrade alerts]
  T4_2 & T4_3 & T4_4 & T4_5 --> T4_6[T4.6 experiments]
  T4_6 --> T4_7[T4.7 demo M4]
  T1_8 --> T5_1[T5.1 shadow]
  T5_1 --> T5_2[T5.2 shadow report]
  T3_1 & T1_9 --> T5_3[T5.3 review queue]
  T5_3 --> T5_4[T5.4 CLI review]
  T1_4 --> T5_5[T5.5 retention + deletion]
  T5_2 & T5_4 --> T5_6[T5.6 demo M5]
  TA & T4_7 & T5_6 & T5_5 --> M7[M7 launch tasks]
  M7 --> V01((v0.1.0))

The critical path runs through the proxy and outcomes (M1), the compiler (M2) and the SDK (M3). M4 and M5 depend mostly on M1, so either can move earlier if M2 stalls.

4. Sequence

The original Gantt chart assumed 10 hours a week from 2026-11-16 and is retired with the dates (see the re-plan above). The order stands:

graph LR
  M123[M1 to M3: done] --> A[Alpha: TA.1 to TA.3 and the gates]
  A --> TV1[TV.1 agent gate]
  TV1 --> M4[M4 Watch]
  M4 --> M5[M5 Compare and review]
  M5 --> M7[M7 Launch]
  M7 --> V01((v0.1.0))

5. Risks

ID Risk Likelihood Impact Mitigation
R1 Langfuse or Arize add native decision-model support. Medium High Ship the alpha as soon as its gates are met, not at the end of the v0.1 plan. Own what they are unlikely to build: finite-sample guarantees, delayed and selective labels, typed questions. Integrate rather than compete: OpenTelemetry export, and an import path from their traces. Publish the research track (research/).
R2 The decision-model category fades. Low–medium. OpenAI went generally available, and TypeSafe, Ollaya and Ollama all moved within two months. High The core (calibration, thresholds, guarantees, drift) works on any probabilities, through the direct record format. Wire adapters stay thin and isolated.
R3 Solo-maintainer bandwidth. High High 25% buffer; re-plan after each milestone; every milestone ships something usable; the cut list below; good-first-issues from M3.
R4 Vendor wire formats change (TypeSafe's spec is at 0.2.0). Medium Medium Recorded fixtures and contract tests per vendor; a monthly changelog check; versioned adapters.
R5 Python misses the ingest or proxy latency targets. Medium Medium Measured in M1 (T1.13): ingest held, the proxy didn't, and its hot path is now Rust (ADR 0015).
R6 A bug makes a guarantee false. Low High (trust) Golden tests; the coverage experiment in CI (NFR-09); a statistician reviews the compiler before the alpha.
R7 Synthetic numbers mislead. Medium Medium Label every synthetic figure as such. Find 1–2 design partners with real traffic before v0.1.0.
R8 A security flaw in the proxy or the key handling. Medium High Threat model; operator allowlists; dependency and secret scans in CI; SECURITY.md with a contact at the alpha.
R9 API costs for real-call tests. Low Low The mock upstream for every test; Ollaya runs locally for free; real calls only in T1.14 and before releases.

Cut list, in order, if behind: 1. Multipart (image) requests in the proxy. 2. The keyboard review session in the CLI (the API stays). 3. Per-option thresholds for choice questions. 4. Shadow traffic, moved to v0.2. 5. Email and Slack alerts (signed webhooks stay).

6. Definition of Done

A task is done when: - the code has tests (unit or property, and golden tests for anything statistical); - CI is green and coverage didn't drop; - the docs that describe it are updated (API reference, a docs page, CLAUDE.md if a convention changed); - the commit is a Conventional Commit that names its FR or NFR ids; - there are no secrets.

A milestone is done when: - every task is done; - its demo in examples/ runs end to end from a clean checkout against the mock upstream (and against Ollaya where it applies); - the acceptance criteria of its user stories pass as tests; - its NFRs are measured and recorded; - estimate against actual is recorded, and the plan is re-based; - it is tagged as a pre-release.

A release is done when: - every milestone in it is done; - the full CI passes, including the security and license checks; - there is a changelog and a semver tag; - images (amd64 and arm64) are on GHCR and packages are on PyPI; - the quickstart works on a fresh VM in 10 minutes or less; - the homepage claims match what shipped; - upgrade notes and known limitations are written.

7. Decided before Phase 5 (2026-11-10)

  1. Tests run in CI. GitHub Actions runs the full suite on every push. Locally, run only lint and single test files: the maintainer's machine is short on memory. Load tests and the nightly experiments never run locally.
  2. The repository is public: github.com/trimset/trimset.
  3. API keys for T1.14, in M1: a TypeSafe key and an OpenAI key, for a few cents of real calls. They are kept out of the repo, in CI secrets.